Refurbishment works

The Male & Female Saunas are complete. Thank you for your patience during the refurbishment works, we hope you are now reaping the benefits.

We now move onto the old Creche area. This is a 5 pronged approach:

1/ Refurbish the Creche corridor

2/ Move the existing corridor lockers into the old Creche corridor and start work on the corridor refurbishment and Beauty Spa Reception area at the bottom of the Beauty Spa stairs

3/ Refurbish main Creche area, this becomes Studio 3

4/ Move Studio 1 into Studio 3 and completely refurbish Studio 1, new floor, ceiling, lights and paintwork.

5/ Move Studio 3 back into Studio 1 and then ‘kit out’ studio 3

These are exciting times ahead of us and we look forward to bringing you the refurbished areas in a timely manner.